Inconsistency of the %Done indicator on tasks
Before:
An inconsistency occurred in the %Done indicator when comparing between the Quick task editor (modal view), Easy Gantt, WBS, and the standard task detail view. This indicator may have differed when viewing the same task using different task editors.
Now:
Fixed a bug in the Quick task editor (modal view). No inconsistencies in the %Done indicator on tasks when viewed using different task editors.
A potential security threat related to a stored XSS within the task title field
Before:
There was a potential security threat related to a stored XSS within the task title field. XSS payload could be triggered at least in two places of the application.
Now:
Fixed.
Resource Dashboard: The User utilization gauge (page module) shows an incorrect maximum range of hours
Before:
In Resource Dashboard, the User utilization gauge (page module) shows an incorrect maximum range of hours in each optional period: 48 hours for 7 days, 184 hours for 30 days, and 520 hours for 90 days. The correct maximum range should correspond to 8 hours per workday.
Now:
Fixed. The maximum range of hours in each optional period corresponds to 8 hours per working day.
Quick task editor: The ❮TAB❯ tag cannot be saved in the Comment field when logging spent time
Before:
When logging spent time using the Quick task editor (the modal view), the ❮TAB❯ tag in the Comment field was not validated and, therefore, the Comment field was mistakenly considered empty. If a comment was required, the spent time could not be saved at all.
Now:
Fixed. The ❮TAB❯ tag in the Comment field is validated and the comment is saved correctly in the spent time entry.
An issue with creating a new task from a task filter
Before:
When a new task was created from a task filter by a user who was not a member of a project defined in that task filter, the task created by that user was unexpectedly placed under a different project, namely the last one, under which this user previously created a task.
Now:
In such a situation, the user is warned that the task will be created under a different project than the one defined in the task filter.
A design issue in the German translation of the Gantt chart
Before:
With long words in the German language, the dates in the Gantt chart overlapped the words.
Now:
Fixed.
Duplicated search field in Administration >> Projects
Before:
Due to a design issue, the search field in the Administration >> Projects section was accidentally duplicated after entering and deleting the searched string from this field.
Now:
Fixed.