A saved filter is not completely applied

Before:
Once a saved filter with a selected time period was applied, the time period used was different than the one saved in the filter.

Now:
Fixed. The time period from a saved filter is applied correctly.

Export of a task's budget does not work properly

Before:
When exporting a task's budget, the exported file contained data from the whole project even when the user selected to export data related to a specific task only.

Now:
Fixed. When exporting a task's budget, the file only contains data related to the specific task, not more or less.

WBS: A task "sticks" to the cursor

Before:
In WBS, after clicking on a task, the task "stuck" to the cursor and the user had to click again to get rid of it.

Now:
Fixed. No problem with a task stuck to the cursor.

Scheduler: A task with a 2-hour estimated time cannot be allocated on the calendar

Before:
In Scheduler, if a task with a 2-hour estimated time was moved to a suggested free slot in the calendar, it automatically returned to the left task list instead, which was not the expected behavior.

Now:
Fixed. No problem with the allocation of a task with a 2-hour estimated time in Scheduler.

The day view in the spent time list shows more days at once

Before:
On a spent time list, when results were shown in the day view and grouped by date, it was supposed that only records from a specific day would be presented in a group. However, more days at once were presented in a group, which was not the expected behavior.

Now:
Fixed. When results are shown in the day view and grouped by date, only one specific day is presented in a group.